Retreat Center

Timeline and areas

  • Refurbishment OF RC
    • December 2025 (RC Kitchen Floor)
    • Male and female dorms
    • Other accommodations
  • RC Kitchen ready for
    • In person retreat in May 2025

Steps (to sort)

(Before WR)

  • Area around RC Kitchen
  • Move Furniture Stores
  • Move storage rooms
  • Move Book Stores
  • Move RC Store ?
  • Move Guest rooms (some rooms are used during the WR)
  • Move Bodhi House Rooms
  • Sangha Room
  • Junk Yard
  • Removing roofing in front and behind the kitchen
  • Removing cold room
  • Get rid of old Cooker, spin dryer (barn) ?

Furniture Store

  • Furniture store emptied by the end of December (furniture and books)

  • Cleaned by the work monk.

Temporary Sala

  • Completely empty for end of December

  • plus 3 rooms to be emptied

  • and clean the place

  • RC keep the grey mat big

Guest Rooms and Bodhi House

  • liaise with Guest Monk Nun and bodhi house and empty the room

  • RC needs 5-6 rooms for helpers (3-5 is taken, 4-(6) plus 17+18)

  • Rooms 12-13-14-15 will be vacated before the WR (10, 11, 12 used already)

    • Need to arrange this room to be ready for the WR

  • As soon as possible, at the end of April (transition down), people go out of RC, bodhi house as well. May Month need to be emptied. Going back to old standard

  • Don't book anyone after the WR?

  • Work monk help with cleaning the rooms of RC

Storage puzzle

  • Move second bay of the workshop to the new workshop first 
  • or using the containers to store the books and furnitures temporarily

Maria's Note about Kitchen

Ideally, the former dining area can be cleared at the beginning of the winter retreat as the floor needs to be looked at and repaired.
That needs to be liaised with the site manager Eleanora

In the DINING AREA (linoleum) are at present : two cupboards RCK6  and RCK7, the big grey Gram fridge B1 (All marked on the attached present kitchen plan)
 and the small freezer next to the big fridge, the chest freezer B3 has stopped working and the little one was taken from the RC kitchen container.
All that needs to be moved into the KITCHEN AREA  (red floor tiles).

There is a counter fridge with drawers next to the back sink.
It needs repairs to its drawers and to be moved to the other side of the sink.

The area between the combi oven and the counter fridge  I need to find a table /cupboard that will fit into the space between that fridge and combi oven.

The previous cupboard will not fit anymore due to the combi oven .
I would like to find out if one can put the filter for the combi oven on the shelf of the combi oven table, as that will free up more space for a longer cupboard.

Everything else, please move out, take off the walls and the ceiling.

If some furnishings, shelves, etc are not being used in the new main kitchen, please let me know. Some of it could be used in the Retreat Centre Kitchen.

 Empty both larders, including big metal cabinet

Empty sangha room except the white cupboards: 

Empty flower shed: but leave the  high up shelves 

The kitchen does not need any of the blue containers nor the walk in fridge behind the kitchen.

There are also the old cooker  from the old kitchen and the industrial spin dryer from the monks' scullery. 
Can they go on eBay, free cycle or taken to the recycling. They are now in the back of the kitchen under the  extracting duct.

Most of the old RC kitchen and dining room furniture will be used again, which is stored in the RC kitchen container.

It would be good   to put the RC kitchen in place and have it as back up for the main kitchen and store surplus main monastery kitchen cupboards etc in the freed space if there will be a storage issue.
It is possible to use the kitchen with RC kitchen equipment as it was used in the past when the old kitchen was refurbished.  

Drawing of Monastery RC kitchen furnishing .png

Inventory

Cupboard 

  
RefDescriptionWDHuse in TKuse in NK
S1Servery with wheels 1836065

S2Servery with wheels 1836065

S3Servery with wheels 1836065

S4Servery with wheels1806065








CK3Cupboard, open, 2 shelves1506090

CK11Drawer set, 3d606090








NS1Cupboard (HW urn)1206585

NS2Cupboard1506587








CK2Cupboard, open, 2 shelves1806590

CK10Drawer set, 3d606589








RCK6Cupboard (servery) with drawers/shelves1536990

RCK7Cupboard (servery) with shelves2327090






















RCK13Cupboard (Water Urn, cups etc), wood1565292not needed
RCK 14Cupboard, wood9260155not needed

Tables

RefDescriptionWDHuse in TKuse in NK
MS3Table with shelf (recycling)1227690

RCK8Table, 1 shelf1227691

CK4Prep table, 1 shelf, 1 drawer1207589

CK5Prep table, 1 shelf, 1 drawer1207589

CK7Prep table, 1 shelf, 1 bottomless drawer1506589

CK6Prep table, 1 shelf1506589

NS3Table (no shelf)906587








CK8Prep table, 1 shelf1806589

CK9Prep table, 1 shelf1206589

CK12Table606090

CK13Table with shelf606090

RCK10Table, no shelf1006090

RCK9Table, no shelf2378090

RCK12Prep table (1 shelf, wood base)19510187

RCK11Prep Table2245985

Equipment

RefDescriptionWDHuse in TKuse in NK
F1Fridge 6560190

F2Fridge 6560190

F3Fridge 3 (glass door)6560196

B1Fridge (ex RC)7090200

B2Freezer 11126588

B3Freezer 2 1626588








RCK17Freezer (RC office)556085maybe
RCK2Countertop fridge907088insert in cupboard row
RCK3Fridge + freezer6065198not needed
RCK18Fridge (RC office)5960184not needed
RCK1Stove (10 fires, 2 ovens)1538091

CK24Wok cooker93105125not needed
CK23Stove (6 fires, 1 oven)918091not needed

Sinks

RefDescriptionWDHuse in TKuse in NK
RCK4Sink (north side)2206088

MS1Sink with shelf (laundry)2076595

NS4Sink (double) with shelf2667091substitute with NS4
CK1Sink with shelf (175)2538092

RCK5Sink (east side)4808092

MS2Sink with shelf (dishwashing)2508293

Other

RefDescriptionWDH
use in TKuse in NK
MS4Steel Trolley9841111


RCK 15Shelf rack w/wheels, 4s6060196


CK21Shelf set with wheels, 5s15040180


NS10-11Wall shelf (2x)1803530in alcove?

CK15-16Wall shelf (2x)903530in alcove?

CK17-20Wall shelf (4x)1203530


NS9Wall shelf1203530


CK22Draining/towel hanger wall shelf802720side of north sink?

CK14Mixer stand (wood)696076


S4Sala trolley (wood)10070110


RCK13Cupboard (Water Urn, cups etc), wood1565292not needed

RCK 14Cupboard, wood


not needed

NS8Broom cupboard (plastic)7043182not needed

RCK 16Shelf rack white12034164throw away!!

Possible dining room chairs

possible dining room chair1.jpg

possible dining room chchai2.jpeg

Time off

Maria: February (ideally)
Jenna: January 

Jenna Notes

Transition: Retreat Centre Household

1) Temporary Furniture Store / RC Men’s Dorm:
* Non-RC Furniture and Books to be removed by end of December at latest.
*  RC Furniture left in room – we will sort this.
* Then Room deep – cleaned by work monk/nun teams (hasn’t been cleaned for 4 years!)
*  IMPORTANT:  Where can furniture and books go? Will Old workshop be empty?
                             

2) Temporary Sala / RC Women’s Dorm:
* If Possible, vacate by end on December?
* Doors in side wall to be reconverted to windows by contractors 
   Hopefully during Winter Retreat Jan or Feb?. (To check with Eleonora about this).
* We will then set up women’s dorm during winter retreat (March)


3) Other Rooms in RC Currently used by Guests and Bodhi House:
* Winter Retreat: It’s Ok for these to be occupied during winter retreat as usual.
*  But we will need some room for RC helpers during this time too. We suggest:
    RC uses about 5 rooms to include 4,5,6 and two of the male guest rooms (17,18)
* This would leave 6 rooms for male winter retreat helpers and 6 for female.
    Guest monk: 16,19, 20, 21, 22, 23; Guest nun: 10, 11, 12, 13, 14 ,15 (see below)
* Note: 3 Rooms off Sala – currently used for storage (13,14,15) to be reconverted to rooms
   For winter retreat female guest use.
* April: We will continue to need some rooms for helpers in April.
   As suggested winter retreat helpers could stay on until the end of April.
   Suggest that from start of April, new guests only booked into Karunasom/ male guest area
   But people staying on after winter retreat can stay on in RC up to end of April if needed.
* We would ask that s rooms are vacated, they can also have a deep clean.
* Also suggest maybe no new Bodhi House bookings in RC from April.
* May: We need to have RC completely vacated by start of May to prepare rooms.
* Items in the RC Rooms to be labelled. NB almost all furniture is RC furniture.
   A few items go to monastery – eg table in room 7.


4) Items to be Returned to RC:
* In Heartwood House there are currently about 6 beds belonging to the RC.
   These were borrowed by a previous Lodgings monk when the monks moved into the
   House as there were no beds there. But on the understanding that they were just on loan 
   And would be given back when retreats resumed.
* So we will be needing them back by the beginning of April at the latest. And the Lodgings
    Monk will need to find some new beds and also mattresses which also came from the RC.
    The bedding belongs to Heartwood.  I will contact the Lodgings monk and copy you in –
    I forgot to mention this when we spoke.      

Return Bed form Heartwood House: A previous lodgings monk had asked to borrow about 6 RC beds and mattresses when the monks moved into Heartwood House (around 2021/22?) on the understanding that they would be returned when we needed them to start up retreats again. So that time has come- or will shortly come! And we will need those beds and mattresses back- I would say around the start of April. So the current Lodgings monk and monks community will need to get some new beds and mattresses from somewhere by early April. 


          

To Do

  • label with tape what is RC, what is SALA
    • Red is RC
    • Yellow is SALA