Skip to main content
Constraints
- RC operational
by?by [Q].end of InputMay from Jenna and Maria2025
- Blue container rented to? [Q]. Input from Caroline (or EST secretary)
- Phase 7b Construction Commencement date - June 2026
- Phase 6s Practical Completion date -> 7th of November
- Budget and contractor for building storage? -> https://www.fittingly.co.uk/
- Budget and contractor for building workshop? [Q]
Input from AAs
Budget and contractor for refurbishing RC? [Q]. Input from EM (no need to know for the Sala transition officer)AAs]